Abstract: When the geological complex area is encountered in the process of coal mine production, in order to avoid the waste of coal resources, the roadway may be excavated along the fault in the design process of the working face, which produces the extremely irregular working face. Taking No.2913 Face of Dongpang Mine as an example, this paper expounded the detection principle, design method and matters needing attention of several common geophysical detection methods. It ensured the safety requirements of the working face in the water prevention and control, and provided some reference for the geophysical detection design in the extremely complex shape working face.
陈 龙. 极不规则工作面下的常用物探方法设计及施工[J]. 煤炭与化工, 2023, 46(7): 48-51.
Chen Long. Design and construction of common geophysical detection methods under extremely irregular working face. CCI, 2023, 46(7): 48-51.