Based on severe mining and wasting of resources in Dianping Mine, mining technology of open-pit roadway with no coal pillar under cutting tip unloading pressure in 5-200 working face was introduced, the traditional two-lane model of long wall mining was abandoned, Directional pre - splitting heading technology was adopted, heading face roadway was retained as the recovery mining roadway of the next working face to realize single mining. The implementation of the technology retained the completed air return roadway as the air return roadway of 5-202 working face, retained 942 m roadway, with more 100 000 t raw coal, providing reference for no-pillar roadway along empty roadway mining
马福杰. 无煤柱沿空留巷在中厚煤层的围岩变形规律研究[J]. 煤炭与化工, 2018, 41(7): 1-6.
Ma Fujie. Study on deformation law of surrounding rock in middle and thick coal seam along empty roadway without coal pillar. CCI, 2018, 41(7): 1-6.