By adopting slurry anchor cable instead of the original hydraulic point column + articulated beam overrun support in the lower roadway of 172404 working face, the slurry anchor cable reinforcement replaced the single pillar and hydraulic support on the basis of the original support structure of the roadway, which improved the utilization rate of the roadway section and reduced the support cost, and provided technical guarantee for the promotion and application of intelligent mining technology in mines.
马登林. 综放工作面注浆锚索超前支护关键技术[J]. 煤炭与化工, 2021, 44(6): 9-11,15..
Ma Denglin. Key technology of grouting cable anchor advanced support at fully mechanized working face. CCI, 2021, 44(6): 9-11,15..