Based on characteristics of large mining height in 18205 mining face, its gas emission sources were analyzed and management measures were proposed. Before operation of gas control roadway, gas released from the working face was treated by borehole extraction in upper corner hanging pipe and roof fracture zone. After application of gas control roadway, gas content was effectively reduced by comprehensive gas control combining with drilling in roof fracture zone, which solved gas overrun problem in upper corner of goaf under pressure.
郭伟强. 大采高综放工作面瓦斯综合治理技术与应用[J]. 煤炭与化工, 2017, 40(7): 121-123.
Guo Weiqiang. Application and technology of comprehensive gas control in fully mechanized mining face of large mining height. CCI, 2017, 40(7): 121-123.