With the development and popularization of large mining height are broken fully mechanized process, The First Mine of Yangquan Coal Group in S8310 working face for the first time test and application of success.According to the mine site environment complex, the first installation cycle is long, adverse to the influence of production, through analysis and research, the downhole move measures, will install S8310 face fully mechanized equipment to S8303 large mining height, put forward the technical way to achieve rapid dismantle and reinstall, and some suggestions on the process of disassembly and installation are given.Practice shows that the project effect is good, to provide technical experience for reference for the similar situation.
李晓宁. 阳煤集团一矿大采高工作面拆除工艺实践和探讨[J]. 煤炭与化工, 2016, 39(2): 116-118,121.
Li Xiaoning. The First Mine mining height demolition technology practice and explore of Yangquan Coal Group. CCI, 2016, 39(2): 116-118,121.