Combined with geological and hydrologic conditions that main inclined shaft crossing, compared with main inclined shaft in technical terms, main inclined shaft construction method fit for the mine was put forward, which provided technical guidance for the construction and favorable condition for the rapid construction of the mine.
李兴才,王书刚. 软岩含水层主斜井井筒施工方法的选择[J]. 煤炭与化工, 2015, 38(4): 15-16,21.
LI Xing-cai, WANG Shu-gang. Soft Rock Aquifer Main Inclined Mine Shaft Construction Method Selection. CCI, 2015, 38(4): 15-16,21.