In order to solve the problem of high ventilation resistance of mine ventilation system in west side of No. 9 coal seam of Gushuyuan Mine and the gas emission in ventilating roadways and the insufficiency of air volume for production, the necessity of mine ventilation reconstruction based on the actual situation of mine ventilation and the mine late production layout were analyzed. And according to the situation of mine, two available schemes were put forward, the best scheme was settled through a comparative analysis.
刘建兵. 古书院矿9号煤层西翼通风系统改造实践研究[J]. 煤炭与化工, 2015, 38(1): 81-83.
LIU Jian-bing. Practice Study on Mine Ventilation System Reconstruction in West Side of No. 9 Coal Seam of Gushuyuan Mine. CCI, 2015, 38(1): 81-83.