With the development of mine exploit, the depth of mining increasing and the size of chamber (water pump house etc.) increasing, the arrangement and support of large cross section chamber became the bottle-neck in high stress area of deep mining. Based on the problem, large section chamber was set under deep goaf, which avoided the high vertical stress of surrounding rock, spray anchor cable and anchor rope combined support concrete spraying scheme was adopted. The research practice showed the deformation of surrounding rock was under control with good effect, provided arrangement and support for mine deep mining of large section chamber.
陈 锋,程高峰. 深部采空区下大断面硐室围岩稳定机理与控制研究[J]. 煤炭与化工, 2014, 37(9): 46-48.
CHEN Feng, CHENG Gao-feng. Study on Large Cross Section Chamber Surrounding Rock Stability Mechanism and Control under Deep Goaf. CCI, 2014, 37(9): 46-48.