| Study on Deep Shaft Fully Mechanized Top Coal Caving Working Face Gob-side Entry Retaining Support Design |
| YANG Yan-jun1, 2 |
| 1. Taiyuan University of Technology, Taiyuan 030024, China; 2. Changcun Mine, Lu’an Huanneng Company, Changzhi 046102, China |
|
|
|
|
Abstract Based on specific fully mechanized caving working face conditions, basic support, roadway support, strengthening support of gob-side entry retaining were designed specifically. High water quick-setting material was adopted, the structure of filling body, packing bags were designed to make the strength of filling body at 12 MPa, which met the needs of work. Tip without coal support design was adopted in roadway support strengthening, ZTC30000/25/50 of the hydraulic support was finally settled. The result showed that the design could control the gob-side entry retaining and provid reference for other deep shaft gob-side entry retaining design.
|
|
|
|
|
|
| [ 1 ] 陈 勇,柏建彪,王襄禹,等. 沿空留巷巷内支护技术研究与应用[ J ]. 煤炭学报,2012,37(6 ):903 - 910.[ 2 ] 柏建彪,周华强,侯朝炯,等. 沿空留巷巷旁支护技术的发展[ J ]. 中国矿业大学学报,2004,33(2 ):183 - 186.[ 3 ] 柏建彪. 沿空掘巷围岩控制[ M ]. 徐州:中国矿业大学出版社,2006.[ 4 ] 康红普,牛多龙,张 镇,等. 深部沿空留巷围岩变形特征 与支护技术[ J ]. 岩石力学与工程学报,2010,29(10 ):1 977 - 1 987.[ 5 ] 张东升,茅献彪,马文顶. 综放沿空留巷围岩变形特征的试验研究[ J ]. 岩石力学与工程学报,2002,21(3 ):331 - 334.[ 6 ] 谢文兵. 综放沿空留巷围岩稳定影响分析[ J ]. 岩石力学与工程学报,2004,23(18 ):3 059 - 3 065. |
|
|
|