| Research and application of roadway gangue filling technology in Xinyuan Mine |
| Liu Xiaojun |
| Huayang New Material Technology Group Co., Ltd., Yangquan 045000,China |
|
|
|
|
Abstract In order to deal with the gangue produced in underground rock roadway excavation, the theoretical calculation and field test methods were used to study the gangue filling in Xinyuan Mine. The results show that the strength of filling body required for roadway filling is not less than 3.1Mpa, so the mining method of gangue filling and high water grouting is determined. Due to the existence of filling body in roadway, the equivalent mining height is used to predict land subsidence. The observation shows that the final subsidence of the ground surface is 32mm and the inclination value is 0.9mm/m. The office building of the ground industrial square is stable without cracks.
|
|
|
|
|
|
| [ 1 ] 刘建功,赵庆彪,张文海,等. 煤矿井下巷道矸石充填技术研究与实现[ J ]. 中国煤炭,2005( 8 ):36 - 38.
[ 2 ] 缪协兴,张吉雄. 矸石充填采煤中的矿压显现规律[ J ]. 采矿与安全工程学报,2007,24( 3 ):1 - 3
[ 3 ] 祁和刚,张 农,李 剑,等. 煤矿“短充长采”科学开采模式研究[ J ]. 煤炭科学技术,2019,47( 5 ):1 - 11.
[ 4 ] 李志江. 新元矿矸石充填开采地表变形规律分析与研究[ D ]. 徐州:中国矿业大学,2014.
[ 5 ] 黄艳利,张吉雄,张 强,等. 充填体压实率对综合机械化固体充填采煤岩层移动控制作用分析[ J ]. 采矿与安全工程学报,2012,29( 2 ):162 - 167
[ 6 ] 孙春东. 超高水材料充填采煤技术[ M ]. 北京:科学出版社,2017. |
|
|
|