Based on the total ventilation roadway support situation of Fengfeng Group, two support plans were compared under high ground stress mining influence, combined with industrial test, data was summarized and analyzed, the result showed that compared with anchor rod (rope) + partial section net spray support scheme, anchor rod (rope) + U whole section steel net spray supporting played a very good control effect on roadway deformation of floor heave and two sides, roadway section shrink rate stayed above 86.3%, and provided a new way for other roadway support plan and parameters setting.
周国岭,吴鹏飞. 高地应力采动影响下不同巷道支护方式对比研究[J]. 煤炭与化工, 2015, 38(2): 101-103.
ZHOU Guo-ling, WU Peng-fei. Study on Different Ways of Roadway Support under High Ground Stress Mining Influence. CCI, 2015, 38(2): 101-103.