| Emergency treatment method for secondary caving area while exposing column in total return airway |
| Ma Zhiyuan1, Li Jingfeng2, Fang Ning2, Zhang Pengfei2 |
| 1. Shijiazhuang Guosheng Mining Technology Co., Ltd., Shijiazhuang 050035, China; 2. Jinda Coal Industry Co., Ltd. of Shanxi Coal Transportation and Sales Group Co., Ltd., Lvliang 032300, China |
|
|
|
|
Abstract In view of the problem of exposing the secondary roof fall area of the collapse column and blocking the main ventilation section in the renovation construction of the total return airway of the coal mine, the filling technology scheme of pre-installing the skeleton of the false roof protection network was adopted in Jinda Mine. By using the reasonable parameter matching of the two grouting materials of filling and reinforcement and the performance advantages of sub-regional and sub-stratigraphic use, the perfect matching with special geological conditions was realized, and the best use effect of grouting materials was brought into play. The combined application of high-power, high-speed pneumatic drilling tools, special grouting drill pipes and super-large displacement, low-pressure pneumatic grouting pumps provided a reliable guarantee for the rapid filling construction of one-time hole-forming and large-volume cavity areas, and shortened the filling process time. It provided a complete set of technical support system of grouting materials, drilling and grouting equipment and construction technology for emergency cut-through construction of caving zone under similar special geological conditions.
|
|
|
|
|
|
| 1 ] 金达煤业有限公司. 总回风巷掘进工作面掘进地质说明书[ R ]. 金达煤业,2021年.
[ 2 ] 金达煤业有限公司. 总回风巷掘进工作面掘进作业规程[ R ]. 金达煤业,2021年.
[ 3 ] 崔志强. 工作面过陷落柱软弱顶板管棚加固技术研究[ J ]. 煤矿现代化,2020( 2 ):35 - 37.
[ 4 ] 刘凤鸣. 固特珑注浆材料在综采面过断层中的应用[ J ]. 能源与节能,2014.( 12 ):182 - 183.
[ 5 ] 马国学. 煤岩体化学注浆加固技术应用研究[D]. 北京. 中国矿业大学(北京). 2007. |
|
|
|