| Research and application of large slope roadway excavation technology |
| Zhang Guanhua |
| Xingdong Mine, Jizhong Energy Co., Ltd, 054000, China |
|
|
|
|
Abstract According to the actual production of Xingdong Coal Mine, it was necessary to excavate a 34° large slope roadway. In this mine, the construction methods such as artificial support construction platform and gangue curtain were made in the heading face, and the gangue was discharged by the rake rock machine and the rear scraper conveyor. The continuous, efficient and safe excavation of the heading face in the rock roadway was realized. The construction task of 70 m excavation was completed within 20 days, which created a precedent for the large slope uphill excavation of the roadway in Xingdong Mine according to the special requirements. The results showed that the existing construction method solved the difficulties in practical work through small reform, which improved the construction efficiency and reduced the labor intensity of workers. It had certain reference and guiding significance for the tunneling construction of other similar large slope roadways.
|
|
|
|
|
|
| [ 1 ] 李爱军. 大倾角上山巷道掘进施工技术[ J ]. 中州煤炭,2007( 1 ):14 - 15.
[ 2 ] 弓海军. 大坡度倾斜巷道掘进施工技术[ J ]. 西部探矿工程,2012( 1 ):131 - 132.
[ 3 ] 尚军超,翟新荣,秦 超. 巷道大坡度掘进施工安全技术措施探析[ J ]. 工程技术,2016( 12 ):143.
[ 4 ] 朱杰明. 几种大坡度巷道掘进法的技术分析[ J ]. 中国矿山工程,1989( 6 ):67. |
|
|
|