| Transient electromagnetic detection construction analysis of gob-side entry retaining working face in Xingtai Mine and its significance of to geological work |
| Li Chao |
| Xingtai Mine, Jizhong Energy Resources Group Co., Ltd.,Xingtai 054000, China |
|
|
|
|
Abstract The No.25305 and 25307 faces in Xingtai Mine were the working faces arranged by gob-side entry retaining, and the detection angle was arranged from gob-side entry retaining to the 2 working faces in the construction of transient electromagnetic. This arrangement had achieved good results in the detection of Xingtai Mine. The maps of each detection angle were analyzed, and the obvious low resistance range was not delineated after check and drilling verification. It had guiding significance for the geological work and transient electromagnetic construction of the mine.
|
|
|
|
|
|
| [ 1 ] 崔焕玉. 瞬变电磁在葛泉矿应用中的典型异常分析[ J ]. 煤炭与化工,2020,43( 10 ):60 - 63.
[ 2 ] 郭培鹏. 瞬变电磁超前探测技术在山西金谷煤矿中的应用
[ J ]. 煤炭与化工,2015( 2 ):94 - 95.
[ 3 ] 李玉宝. 环工作面采动破坏影响圈采前立体探测技术[ J ]. 煤炭与化工,2014,37( 1 ):10 - 13,92.
[ 4 ] 孙吉益,李玉宝,李文峰,等. 井下瞬变电磁技术在含水陷落柱治理中的应用[ J ]. 华北科技学院学报,2009( 4 ):47 - 50. |
|
|
|