| Xingdong Mine Recovery Working Face Gas
Governance Technology |
| LIANG Jian-min1, HAN Guan-qiao2 |
| 1. Jizhong Energy Corporation Ltd., Xingtai 054000, China; 2. Mine Safety Department, Jizhong Energy Corporation Ltd., Xingtai 054000, China |
|
|
|
|
Abstract Xingdong Mine 2127 fully mechanized working face was in initial recovery, gas in upper corner was high, which seriously affected the working face recovery. Based on this problem, through comprehensive comparison, through adjusting the way of ventilation system and gas drainage solved the gas overrun problem, which ensured working face safe recovery and provided reference and experience for gas control under the similar condition.
|
|
|
|
|
|
| [ 1 ] 俞启香. 矿井瓦斯防治[ M ]. 徐州:中国矿业大学出版社,1992.[ 2 ] 刘新德,姚海飞,马 超,等. 张集北矿首采工作面瓦斯涌出规律分析[ J ]. 矿业安全与环保,2012,39(1 ):49 - 50.[ 3 ] 王忠奎. 工作面瓦斯涌出量预测及瓦斯来源分析[ J ]. 矿业安 全与环保,2008,35(3 ):54 - 56. |
|
|
|