| Study on support technology of cutting roof pressure relief gob-side entry nor coal column working face |
| Gu Jiliang |
| Xingtai Mine, Jizhong Energy Corporation Ltd, Xingtai 054000, China |
|
|
|
|
Abstract In the process of working face recovery, the scope and intensity of dynamic pressure in the two roadway of the working face were different. After mining, the coal seam roof started to bend, sink and collapse, and it took some time from roof collapse to stabilization, therefore, different locations of the roadway in the process of leaving the roadway not only needed to strengthen the original support of the roadway, but also needed to use temporary support to ensure the stability of the roof of the roadway. According to the different force characteristics of the surrounding rocks of the roadway along the gob-side entry in Xingtai Mine, the roadway was divided into 3 zones, over-front support zone (20 m before the working face), over-back temporary support zone (0~100 m after the frame) and roadway stabilization zone (after 100 m after the frame), and different strengthening support measures were taken in different zones according to the actual situation.
|
|
|
|
|
|
| [ 1 ] 孙恒虎,赵炳利.沿空留巷的理论与实践[ M ]. 北京:煤炭工业出版社,1993.
[ 2 ] 华心祝. 我国沿空留巷支护技术发展现状及改进建议[ J ]. 安徽理工大学学报,2006. 34( 12 )78 - 81. |
|
|
|