| Factors affecting rapid mining and prevention and control measures of comprehensive roadway in Guotun Mine |
| Zhao Renbao 1, Wang Minghui 1, Tao Guangzhe 2 |
| 1. Guotun Mine, Shandong Energy Mining Group, Yuncheng 274700, China; 2. School of Mining Safety and Engineering, Shandong University of Science and Technology, Qingdao 266590, China |
|
|
|
|
Abstract In view of the problems of mining succession and low mining rate caused by the slow roadway excavation in Guotun Mine, the transportation roadway in the second mining area of the mine was taken as an example, combined with the geological production conditions of the test roadway, and the comprehensive investigation was adopted to analyze the main influencing factors and prevention and control measures for rapid mining. The research showed that the main influencing factors were complex geological structure, unreasonable design and support, complicated transportation system, single auxiliary transportation form, and immature personnel equipment management. Based on this, the prevention and control measures such as strengthening the geological prediction and forecasting, optimizing the construction process, optimizing the auxiliary transportation system, and innovative management concepts were proposed, which effectively solved the existing problems and provided reference and guidance for similar mine rapid mining projects.
|
|
|
|
|
|
| [ 1 ] 张忠国. 煤巷快速掘进系统的发展趋势与关键技术[ J ]. 煤炭科学技术,2016,44( 1 ):55 - 60
[ 2 ] 赵学社. 煤矿高效掘进技术现状与发展趋势[ J ]. 煤炭科学技术,2007 ( 4 ):1 - 10.
[ 3 ] 马长乐,袁龙飞,张 羽,等. 大断面煤巷快速掘进施工工艺[ J ]. 煤矿安全,2013( 5 ) :98 - 100.
[ 4 ] 田 龙. 煤巷快速掘进技术的应用研究[ J ]. 煤矿现代化,2013( 6 ) :87 - 89
[ 5 ] 李 刚, 牛 磊, 李文龙. 煤矿硬岩巷道快速掘进技术研究[ J ]. 煤炭科学技术, 2018, 46( 11 ):18 - 25.
[ 6 ] 刘跃东, 林 健, 杨建威,等. 基于掘锚一体化特厚顶煤巷道快速掘进与支护技术[ J ]. 煤炭科学技术, 2017( 10 ):60 - 65.
[ 7 ] 杨仁树. 我国煤矿岩巷安全高效掘进技术现状与展望[ J ]. 煤炭科学技术,2013,41( 9 ) : 18 - 23.
[ 8 ] 聂晓飞, 闫高峰, 宋育刚,等. 大断面煤巷快速掘进技术[ J ]. 煤炭科学技术, 2013( s2 ):141 - 142. |
|
|
|