| Numerical simulation study on roadway support of No.8 coal seam in southern No. 4 mining area of Xiqu Mine |
| Wang Yanfei |
| Xiqu Mine, Xishan Coal and Electricity Corporation Ltd., Gujiao 030200, China |
|
|
|
|
Abstract No.8 coal seam of 18401 working face of Xiqu Mine of Xishan Coal and Power Group was taken as the research object, the research method of field application of RFPA numerical simulation technology and support scheme was adopted. The results showed that the stability of the surrounding rock of the roadway was inextricably linked with the strength and rigidity of the supporting material. The joint support scheme of the roadway effectively controlled the development of the surrounding rock cracks of the roadway. The surrounding rock of the roadway was basically 25 days after mining. The deformation was kept constant and the stability was controlled.
|
|
|
|
|
|
| [ 1 ] 李世平.岩石力学简明教程[ M ].徐州:中国矿业大学出版
社,1986.
[ 2 ] 许家林.岩层移动与控制的关键层理论及其应用[ D ].徐
州:中国矿业大学采矿工程系,1999.
[ 3 ] 侯朝炯,勾攀峰. 巷道锚杆支护围岩强度强化机理研究[ J ].
岩石力学与工程学报,2000,19( 3 ):342 - 345.
[ 4 ] 张恩强,张建忠,刘金辉. 煤矿上行开采覆岩运动规律研
究[ J ]. 西安科技大学学报,2011,( 3 ):258 - 262.
[ 5 ] 李本奎,苏学贵,李浩春,等. 含有软泥入侵的多溶洞型顶板
巷道稳定控制研究[ J ]. 金属矿山,2014,( 8 ):145 - 146.
[ 6 ] 冯国瑞,任亚峰,王鲜霞,等. 白家庄煤矿垮落法残采区上 行开采相似模拟实验研究[ J ]. 煤炭学报,2011,36( 4 ):
544 - 550.
[ 7 ] 杨 涛. 煤巷围岩稳定性控制技术研究[ D ]. 青岛:山东科技
大学,2011年.
[ 8 ] 姚 锐. 硬顶条件下煤巷围岩稳定性模拟研究[ D ]. 太原:太
原理工大学,2012年.
[ 9 ] 张德辉. 阜新矿区煤巷锚杆支护技术研究[ D ]. 辽宁工程技术
大学,2004年.
[ 10 ] 李忠亮. 煤巷围岩控制与锚网支护技术的研究[ D ]. 包头:内蒙古科技大学,2012年. |
|
|
|