Abstract Based on the increasing mining depth and mining pressure of Dongpang Mine, leading to the long period of roadway construction, underground support parameters and corresponding mining and transportation equipment were designed, based on the geological condition of working face, the reasonable mining technology was set, mining ahead achieved 240 m per month, greatly reduced materials and labor in second anchor net building.
|