Abstract Based on big pressure of roadway roof and wall, fast deformation, large fully mechanized support shipping work preparing workload, long support transportation time, Guo’erzhuang Mine was taken as an example, its 22108 working face transportation adopting stents fission transport and laying track in eye cut, which reduced the scaffold preparation time before shipping, on stents winch, double speed winch would cut transportation time.
|