Abstract Combined with Chensilou Mine north No. 8 mining area coal bunker upper was chamber with good support, lower was waste rock chamber with good support, reverse well drilling method digging hole construction was adopted. The application showed that the technology improved the degree of mechanization, tunneling efficiency increased 2 times, shortened the construction period, speeded up the mining area coal bunker construction speed, which provided the relevant experience for coal bunker construction under similar conditions.
|