| Overall Top Beam Suspended Bracket Face New Installation Process Exploration |
| XU Song-chao, CAI Yuan-chang |
| Dayou Energy Corporation Ltd., Sanmenxia 472431, China |
|
|
|
|
Abstract In order to solve suspended bracket face normal installation method cutting roadway maintenance under the high stress in the construction process, and after repeated demonstration, the "installation" during tunneling construction technology was put forward, which successfully avoided cutting roadway maintenance, the field practical proved it was feasible and achieved good social benefits and economic benefits.
|
|
|
|
|
|
|
|
|