| Application of deep hole blasting pre-splitting roof pressure relief gob-side entry retaining technology |
| Yang Haojie |
| Gequan Mine, Jizhong Energy Resources Group Co., Ltd., Xingtai 054100, China |
|
|
|
|
Abstract In order to reduce the waste of resources and ensure the mining replacement of the mine, the deep hole blasting roof pressure relief gob-side entry retaining technology was applied in No.1727 Face transportation roadway of Gequan Mine. Through the deep hole blasting pre-splitting roof in the advanced working face, the roof formed through cracks in the direction of the roadway. When the roof fell, the stress conduction was cut off to achieve the purpose of roof pressure relief and reduce the mining deformation of the roadway. With the support technology of the retaining roadway and the grouting sealing technology of the goaf, the gob-side entry retaining was realized. The gob-side entry retaining was 505 m in total. Through observation and data analysis, the change of surrounding rock in the range of 100 m behind the working face was large. After 100 m, the surrounding rock gradually tended to be stable, and the overall section of the retaining roadway exceeded 90 % of the original roadway, which satisfied the use of No.1729 working face transport roadway. This technology could provide reference for other similar mines.
|
|
|
|
|
|
| [ 1 ] 武腾飞. 受采动顶板回采巷道围岩稳定性分析及控制技术研究[ D ]. 淮南:安徽理工大学,2015.
[ 2 ] 张弘弦. 同忻煤矿切顶卸压沿空留巷技术应用[ J ]. 煤矿现代化,2021( 6 ):175 - 178.
[ 3 ] 曹冬冬. 12408 工作面切顶卸压沿空留巷技术研究与应用[ J ]. 煤,2021,30( 2 ):17 - 19,27.
[ 4 ] 张荣立,何国纬,李 铎,等.《采矿工程设计手册》[ M ]. 北京:煤炭工业出版社. 2003.
[ 5 ] 李丰廷. 亿欣煤业坚硬顶板预裂爆破切顶留巷技术与试验[ J ]. 煤,2021,30( 1 ):70 - 71. |
|
|
|