Yuxi Mine belongs to coal and gas outburst, two quaternity outburst prevention should be conducted before mining, crossing layer pre-drilling coal seam gas was adopted in working face roadway, position of the bottom suction lane and the angle of the perforation hole are the key of solving construction difficulty and reduce invalid drilling. Reasonable level selection of bottom suction roadway and optimized drilling were given based on comparison and calculation, with good economic benefit after construction.
张建林. 首采和准备工作面底抽巷及钻场设计优化研究与应用[J]. 煤炭与化工, 2018, 41(2): 84-87.
Zhang Jianlin. Optimized research and application of bottom drainage roadway and drilling design of initial mining and prepared working face. CCI, 2018, 41(2): 84-87.