| Study on control technology of surrounding rock in fracture zone of return-air roadway |
| Liu Chunji |
| Linfen Hongda Mining Co., Ltd., Jinneng Holding Coal Industry Group, Linfen 041000, China |
|
|
|
|
Abstract In order to solve the problems that may occur in the fracture zone of No.21510 return-air roadway, such as sheet wall, roof collapse and water gusher, the geological conditions of roadway excavation were analyzed. FLAC3D software was used to numerically simulate the vertical stress distribution and plastic zone development of roadway during normal excavation and fault crossing. The results showed that: compared with the normal section, the development range of the surrounding rock stress and plastic zone increased significantly during over fault tunneling, and the fault activation expanded the influence range of tunneling failure. The stability of surrounding rock was comprehensively controlled by using the method of circular grouting and "combined support with anchor net and cable beam", and the control effect was observed. During the observation period, the maximum and maximum displacement of the left and right sides of the roadway were 7.22mm and 10.68mm respectively, and the maximum displacement of the top and bottom was 21.9mm, indicating a good control effect of surrounding rock.
|
|
|
|
|
|
| [ 1 ] 曹运兴,张海洋,张 震,等. 正断层上盘煤与瓦斯突出特征与地应力场控制机理[ J ]. 煤田地质与勘探,2022,52( 4 ):61 - 69.
[ 2 ] 廖志恒. 深井巷道断层对冲击地压的影响分析[ J ]. 矿业安全与环保,2018,45( 1 ):61 - 64.
[ 3 ] 李海燕,胥洪彬,李召峰,等. 深部巷道断层涌水治理研究[ J ]. 采矿与安全工程学报,2018,35( 3 ):635 - 641,648.
[ 4 ] 赵仁乐,张国朋,段会玲,等. 断层破碎带冒顶巷道支护技术研究[ J ]. 煤炭工程,2018,50( 3 ):42 - 46.
[ 5 ] 张 鹏,朱学军,孙文斌,等. 采动诱发充填断层活化滞后突水机制研究[ J ]. 煤炭科学技术,2022,50( 3 ):136 - 143.
[ 6 ] 潘伟鹏,华心祝,刘 斌,等. 桃园煤矿综采工作面过断层巷道注浆加固技术研究[ J ]. 煤炭工程,2023,55( 7 ):58 - 65.
[ 7 ] 宋卫华,邸春雷,邓兆睿. 动静载组合下巷道过断层破碎带支护技术[ J ]. 煤田地质与勘探,2019,47( 6 ):135 - 143.
[ 8 ] 王红浩,王宏耀,王明甫,等. 松动爆破在硬煤综采工作面过断层技术中的应用[ J ]. 煤炭工程,2018,50( 2 ):70 - 72,77. |
|
|
|