| Steeply Inclined Thick Coal Seam Fully-Mechanized Caving Mine Pressure Regularity Numerical Simulation Research |
| DENG Peng-hai, WANG Peng,CAO Peng, ZHAO Hai-xiao,WANG Yu-jia,LI Yu-zhi |
| 1. School of Safety and Resources Engineering, China University of Mining and Technology, Beijing 100083, China;2. School of Geoscience and Surveying Engineering, China University of Mining and Technology ( Beijing ) , Beijing 100083, China |
|
|
|
|
Abstract When steeply inclined thick coal seam was taken by using the fully-mechanized mining, there were mix horizon and same horizon, two types of roadway layout, the two way working face of law of mine pressure appearance, top-coal caving and roadway, mine pressure appearance were quite different. Through UDEC4.0 numerical simulation analyzing mix horizon and same horizon under the initial mining and abutment pressure distribution law on both sides near the working face, overlying top-coal movement rule and rule of roadway roof caving mining, the results proved that the first mining face mix horizon top coal caving was superior to same horizon, but, the former lower bearing pressure was larger than the latter; mix horizon the first mining face roadway pressure was big, with hard maintenance of roadway, whereas, the near work along the groove on the surface of the mine pressure was small, which is in favor of roadway maintenance.
|
|
|
|
|
|
| [ 1 ] 谢俊文,高小明,上官科峰.急倾斜厚煤层走向长壁综放开采技术[ J ].煤炭学报,2005,30(5):3 - 7.[ 2 ] 杜计平,孟宪瑞.采矿学[ M ].徐州:中国矿业大学出版社,2009.[ 3 ] 赵景礼.厚煤层错层位巷道布置采全厚采煤法的研究[ J ].煤炭学报,2004,29(2):16 - 19.[ 4 ] 王志强.厚煤层错层位相互搭接工作面矿压显现规律研究[ D ].北京:中国矿业大学(北京),2009.[ 5 ] 张艳伟,邢 望.急倾斜煤层工作面应力分布与破坏特征数值模拟[ J ].煤矿安全,2013,44(1):34 - 36.[ 6 ] 陈光升.浅谈厚煤层错层位巷道布置采煤法[ J ].煤炭工程,2006(11):51 - 53. |
|
|
|