| Feasibility study on safe mining under water in Xiahuo Mine |
| Sun Dianyu |
| Lu’an Coal Industry Department, Jinneng Holding Coal Industry Group, Changzhi 047500, China |
|
|
|
|
Abstract In order to study the safe mining feasibility of working face in Xiahuo Mine under Tianliang River on the ground, it was confirmed that the development height of water conduction fracture zone was 70 m in normal section through theoretical calculation and field measurement, and 185.8 m rock pillars remained their original permeability above the protective layer and under the bedrock weathering zone. Through the mining practice in No.2306 face, the water filling of working face was mainly roof fissure water, and the river would not have a direct impact on the water filling of underground working face through ground mining cracks. The analysis demonstrated that the fully mechanized caving mining under Tianliang River was safe and feasible.
|
|
|
|
|
|
| [ 1 ] 鞠金峰,许家林,李全生,等. 我国水体下保水采煤技术研究进展[ J ]. 煤炭科学技术,2018,46( 1 ):12 - 19.
[ 2 ] 樊振丽. 纳林河复合水体下厚煤层安全可采性研究[ D ]. 北京:中国矿业大学(北京),2013.
[ 3 ] 国家安全生产监督管理总局,国家煤矿安全监察局. 煤矿防治水细则[ M ]. 北京:煤炭工业出版社,2018 .
[ 4 ] 滕永海,高德福,朱 伟,等. 水体下采煤[ M ]. 北京:煤炭工业出版社,2012.
[ 5 ] 许延春,刘世奇. 水体下综放开采的安全煤岩柱留设方法研究[ J ]. 煤炭科学技术,2011,39( 11 ):1 - 4,22. |
|
|
|