| Construction technology of sudden water control by deep hole grouting with high pressure in abandoned frozen drilling hole |
| Su Yong1, Li Genqiao2 |
| 1. Tenth Engineering Office of China Coal Energy Company Limited, Handan 056003, China; 2. Dahaize Mine,
Yulin 719000, China |
|
|
|
|
Abstract Aimed at construction sudden water accident in ventilation connecting roadway of main vertical shaft bunker upper port of Dahaize Mine,with engineering geology comparison on site,frozen construction and survey drilling adopted to check,it was concluded that the sudden water occurrence was owing to No.Z37 abandoned frozen drilling hole encountered when ventilation connecting roadway was constructed. The water inflow reached 155m3/h. When grouting and sealing technology with deep hole and high pressure was adopted,the water inflow reduced to 0.3 m3/h after grouting,which realized quick sealing and achieved satisfactory construction result. The technology provided reference for similar sudden water control by grouting .
|
|
|
|
|
|
| 1 ] 李 刚,李银桥,王世春,等. 千米深立井壁后深孔高压注浆堵水技术[ J ]. 建井技术,2004( 5 ):1 - 4.
[ 2 ] 张伟利. 井筒套内壁施工通风优化[ J ]. 内蒙古煤炭经济,2018( 13 ):120,131.
[ 3 ] 陈德明,段安新. 大直径冻结井筒单层井壁注浆堵水技术研究[ J ]. 煤,2014,23( 1 ):1 - 3,41.
[ 4 ] 季志才,王维和. 石人沟铁矿-300 m至-405 m水平电梯井涌水治理[ J ]. 电子世界,2013( 18 ):216 - 217.
[ 5 ] 滕兴成,曹佳庆,胡玉贺. 隧道涌水预测及整治技术[ J ]. 智能城市,2019,5( 16 ):174 - 176.
[ 6 ] 贺振宇,郭佳奇,陈 帆,等. 隧道典型致灾构造及突水模式分析[ J ]. 中国地质灾害与防治学报,2017,28( 2 ):97 - 107. |
|
|
|