| Analysis and study on blasting technology of rapid roadway excavation |
| Huo Shiying |
| Meiyukou Coal,Jinneng holding Coal Group, Datong 037000, China |
|
|
|
|
Abstract In order to solve the problem low tunneling efficiency in the process of roadway excavation, the double wedge inclined hole cutting method was used for blasting. The blasting process parameters were analyzed in detail and the initiation sequence was set. Through practical application, the results showed that after using the double wedge inclined hole cutting blasting scheme, the average footage increased from 1.2 m to 1.8 m before the test, and the blast hole depth increased from 1.5 m to 2.0 m, The utilization rate of blast hole increased from 85% to 90%, which improved greatly in roadway forming, and the blasting effect was remarkable.
|
|
|
|
|
|
| [ 1 ] 孙传军,郑思达.岩巷快速掘进技术研究[ J ]. 江西煤炭科技,2010( 4 ):39 - 41.
[ 2 ] 辛国安. 中深孔爆破在新集一矿硬岩大断面巷道快速掘进中的应用[ J ]. 煤矿开采,2014,19( 2 ):73 - 76.
[ 3 ] 宗 琦,任庆峰. 煤矿硬岩下山巷道掘进中深孔爆破技术试验研究[ J ]. 爆破,2011,28( 2 ):49 - 52.
[ 4 ] 李宇光. 大峰采区露天煤矿爆破参数设计及应用[ J ]. 陕西煤炭,2016,35( 1 ):59 - 62. |
|
|
|