Abstract In order to master the special complex thick seam coal wall rib spalling law of fully mechanized working face, based on the analysis of the fully mechanized caving stoping technology and mechanical equipment, through observation of the relationship between coal seam advancing and rib spalling depth and rib spalling rate during periodic working face with pressure and non-periodic working face with pressure, mining face rib spalling depth and rib spalling rate distribution law were concluded, which provided a reliable scientific data to improve the stoping technology and mining face safety production.
|
|
|
|
|
|
| [ 1 ] 吴永平. 大同矿区特厚煤层综放采场矿压显现规律研究 [ J ]. 煤炭科学技术,2008,36(1):8 - 10.[ 2 ] 黄庆国. 塔山煤矿特厚煤层综放开采关键技术 [ J ]. 煤炭科学技术,2009,39(2 ):22 - 24.[ 3 ] 黄庆国,高 峰,张 磊. 特厚煤层综放工作面大断面切眼支护技术[ J ]. 煤炭科学技术,2011,39 (5):34 - 37.[ 4 ] 侯建国,白云虎,刘一博. 软煤大采高综采煤壁片帮机理与控制[ J ]. 矿业安全与环保,2011,38(6):23 - 25.[ 5 ] 田取珍,张爱绒,路全宽,等. 厚煤层大采高综采工作面煤壁稳定性研究[ J ]. 太原理工大学学报,2012,43 (1):73 - 76. |
|
|
|