Abstract Linxi Mine with large mining depth and commonly tectonical fault, especially with large fault, severely affecting the normal mining. 1021 fully mechanized working face of Linxi Mine was taken as example, the technical measures of reverse fault with large fall mining were introduced. The practice showed that the technology, with good implementation effect, provided reference for fully mechanized working face crossing large fault under complex geological condition.
|