| Scheme Analytics of Improving Mining Rate of Fusheng Mine |
| WANG-zhen, GENG Hui-xing, YAN-bin, YANG Ben-sheng |
| School of Resources, Hebei University of Engineering, Handan 056038, China |
|
|
|
|
Abstract In order to solve the problem of low mining rate in integrated mine, this paper took for the Husheng mine in Lu’an group a background. The theoretical analysis, numerical simulation and empirical method were used generally. The original design from two sizes was optimized, including the width of coal pillar and the mining methods .The width of coal pillar changed from 30m into 20m. The slice mining was changed into whole height mining. The mining rate was improved 6.1% after the optimization. The improving of mining rate was significant.
|
|
|
|
|
|
| [ 1 ] 梁文江. 论影响回采工作面回采率的因素及对策[ J ] . 能源与技术. 2012(3 ):56 - 57.[ 2 ] 崔廷锋,张 魁,徐新斌. 大采高工作面回采巷道护巷煤柱合理宽度研究[ J ] . 中国矿业,2012,21(8 ):88 - 90. [ 3 ] 钱鸣高,石平五,许家林,等. 矿山压力与岩层控制[ M ] . 徐州:中国矿业大学出版社,2011.[ 4 ] 王学军,钱学森,马立强,等. 厚煤层大采高全厚开采工艺研究与应用[ J ] . 采矿与安全工程学报,2009,26(2 ):212 - 216.[ 5 ] 李宗翔,鲁忠良,魏建平,等. 厚煤层分层开采与综放开采瓦斯涌出量对比分析[ J ] . 中国矿业,2006,15(6 ):43 - 45.[ 6 ] 潘建国. 杭来湾矿3号特厚煤层采煤方法选择研究[ J ] . 中国矿山工程,2012,41(5 ):42 - 44.[ 7 ] 边 强 . 一次采全高和放顶煤工艺采出率问题分析[ J ] . 煤炭科学技术,2007,35(2 ):101 - 104.[ 8 ] 齐俊德. 采煤方法的合理选择和实践[ J ] . 矿冶,2007,16(3 ):14 - 17.[ 9 ] 章 元,夏必培.一次采全高综采与放顶煤综采效果比较[ J ] . 煤矿开采,2008,13(3 ):31 - 33. [ 10 ] 孟宪锐,王鸿鹏,刘朝晖,等. 我国厚煤层开采方法的选择原则与发展现状[ J ] . 煤炭科学技术,2009,37(1 ):39 - 44. |
|
|
|