| Analysis of crowded hydraulic support reasons in large height mining face and prevention technology in complicated geological condition |
| Hou Xiangjian, Li Xiaoping, Yu Haiyang, Shi Wenpeng |
| Dongtan Coal Mine Yankuang Coal Corporation Ltd., Zoucheng 273512, China |
|
|
|
|
Abstract During period of mining in 63上04 large height mining face, Dongtan Coal Mine occurred phenomenon of crowded hydraulic support in working face because of syncline structure, water spraying in the roof, the large mining height and heavy equipment, which brought great difficulties to normal production. Through analyzing the reasons comprehensively, technical proposal of using side guard cooperate with monomer to adjust hydraulic supports was put forward and problem of crowded hydraulic support in working face was completely solved. Its impressive implementation effect provided valuable experience to development of fully mechanized coal mining in large cutting height.
|
|
|
|
|
|
| [ 1 ] 兰云峰. 软煤层7.0 m大采高工作面倒架原因分析及防治技术[ J ]. 煤矿开采,2014(8 ):115-118.
[ 2 ] 张丰杰,张占涛. 复杂地质条件下大采高综采面支架倒架原因及对策[ J ]. 煤炭技术,2015(3 ):232-234.
[ 3 ] 宋维德. 大倾角、大采高条件下重型支架倒架预防及处理技术[ J ]. 煤炭科技,2008(1 ):46-47.
[ 4 ] 张吉军. 大倾角“三软”厚煤层综放工作面支架挤架倒架探析[ J ]. 西北煤炭,2004(5 ):45-47.
[ 5 ] 张存杰.大倾角综采工作面挤架歪架处理技术[ J ]. 山东工业技术,2016(6 ):13. |
|
|
|