Abstract Based on the experiment on site of Da’anshan Mine, combined with geological conditions, anchor bolt + long anchor rope was adopted to conduct the industrial experiment, by monitoring surrounding rock surface displacement and the anchor strength of anchor bolt and rope of 4 different position in roadway, the roadway deformation got stable after 25 days, anchor strength achieved stable after 30 days of support, but not achieving the designed anchor strength, the monitoring result showed that the support plan was feasible.
|